CCI-000494
CCI-000494 Definition
| Status | |
| Type | CheckType.policy |
Master Assessment Datasheet
Implementation Guidance
Determine if: - the contingency plan for the system is tested [CP-04_ODP[01]; frequency of testing the contingency plan for the system is defined]. - [CP-04_ODP[02]; tests for determining the effectiveness of the contingency plan are defined] are used to determine the effectiveness of the plan. - [CP-04_ODP[03]; tests for determining readiness to execute the contingency plan are defined] are used to determine the readiness to execute the plan.
Validation Procedures
Examine: [SELECT FROM: Contingency planning policy; procedures addressing contingency plan testing; contingency plan; contingency plan test documentation; contingency plan test results; system security plan; other relevant documents or records]. Interview: [SELECT FROM: Organizational personnel with responsibilities for contingency plan testing, reviewing, or responding to contingency plan tests; organizational personnel with information security responsibilities]. Test: [SELECT FROM: Organizational processes for contingency plan testing; mechanisms supporting the contingency plan and/or contingency plan testing].